These meeting minutes were taken by Barry Lewin, Bellcore. Thanks, Barry
Walt
Meeting minutes - ICC Test Team meeting - June 12, 1997, 350 Orleans,
4th Floor, Chicago (hosted by
Ameritech) [approximately 17 attendees]
Agenda:
1. Action Items
2. FCC Guidelines Letter
3. NIIF update; review of test plan
4. Operator Services (incl. LIDB)
5. Test plan update (matrix)
6. Number pooling
7. Next Meeting
Action Item 1. Review of Action Items:
Issue 006a - NPAC Test Plan
Walt will be going to next week s NPAC meeting. He hopes to get a
response then.
Issue 12 - Choke network -
Desire to have a region wide choke network has not been adopted and it
is unclear if testing during the trial is appropriate. Although it is
useful to have test scripts for this, it appears inappropriate to test
during the trial. At least in MSA 1, the choke network solution as
discussed won t be implemented (in an LRN environment). To discuss with
Barry Bishop (Operations Committee) agreed that this issue is not
LRN/LNP and should be closed. Barry agreed to write wording regarding
the resolution for archive
purposes.
Issue 18 - E911 test cases
The test cases have been written, provided to Bill Belshaw, on
ported.com under the 911 section. The scripts will be in the 1.4 version
of the test plan (the 1.4 version
hasn t been released as yet).
Issue 24 - Failure scenario testing - to be discussed during FCC
Guidance discussion.
Issue 25 - LEC-to-LEC interface tests
Bill Belshaw working on these. It is assumed these will be in version
1.4.
Issue 26 - Test scripts for porting process flows
Bill Belshaw working on these. It is assumed these will be in version
1.4. These flows (to be useful) should be submitted before the July
meeting. Walt to contact Bill to determine if they will be available
before July meeting. Jim Joerger spoke with Bill Belshaw and reported
that porting flows should be
available for the SPOC meeting next week.
Issue 28 - Test cases for post dial delay
Dick sent info to Bill. CLOSED
last time.
Issue 29 - Test cases for LSMS section
CLOSED last time.
Issue 30 - SCP looping test
Walt will take this item and build script(s) based on what he does
internally. This will be discussed
again in FCC guidance discussion.
Issue 32 - List of NXXs and DNs for each company
Dick has a great deal of information from several participants. The NPAC
is looking for this info. Dick pointed out that the info would go to the
NPAC regardless and this action item is just a back up. We (Walt and
Dick) will raise this issue at
next week s NPAC meeting.
Issue 34 - Picture reference for each test case
The only area of concern is with ISDN. Because only Ameritech (and
perhaps Sprint) wants to test ISDN, it may not be a major concern. Walt
was planning to publish (via conference call) the tests that will be
run. This will close after the
walk through of the ISDN scripts.
Issue 44 - SCP committee to write looping test script
CLOSED last time.
Issue 45 - Develop test procedure for looping test
CLOSED last time but the Test Team may want to re-consider a looping
test.
Issue 46 - Update to Section 4.4
Redundant with porting test
scripts (issue 26). CLOSE issue 46.
Issue 47 - Update to section 4.3 for Operations
To ask Barry Bishop of status. Per Barry, this is still awaiting FCC
desires.
Issue 48 - Is there a TTN issue?
Remains open with Walt and Jeff not connecting. The resolution does not
impact the Chicago MSA test, although it may result in subsequent test
script changes later. Walt will attempt to connect with Jeff again.
Nevertheless, this issue will be
CLOSED.
Agenda item 2. FCC Guidance document
Background discussion: FCC cam to Brent Struthers looking to provide
input to trial without impacting the very tight schedule. The FCC is not
asking us to do much - it is more of an impact on the report than the
testing.
1. The report should accurately evaluate LRN or other solutions. The
trial will focus on LRN.
2. This is a repeat of many of our internal issues/guidelines. Relative
to multiple database failures, they are looking for multiple LSMS
failures and the effect on switches. Action item 47 (rolling/cascading
overloads) addresses this item. [note that it is referred to as NPAC
databases and they intend it to mean LSMS]. Question centered on this
being destructive testing while live traffic is moving. Dick pointed out
that wording could be put together that discussed the known result of
various multiple failure scenarios and why it wasn t tested. Barry
suggested that the SCP folks provide this wording.
Item (b) discusses switch-based failure scenarios. This wouldn t be done
in a live network either. Optional responses are to develop off-line
test scenarios or provide wording indicating why such testing wasn t
done. Another option is to ask the vendors to provide results of
internal failure scenarios or to refer this item to the Network Test
Committee (NTC). Jim Joerger pointed out that without resolution of the
funding issue, it is highly unlikely that the NTC will do any testing
this year.
Item (c) relates to test conditions and "pre-conditioning" of networks.
We have said that everyone must pre-test and we have allocated
sufficient time before cooperative testing begins (e.g., two months of
in-house soaking in advance of testing). As long as we can run through
all the porting scenarios, we probably addressed the installation piece.
Barry Bishop agreed that appropriate wording could be put together to
meet this FCC need.
3. This addresses an item similar to 2c.
4. This should be covered by the NPAC team(?). The NPAC will not let
them do uploads unless the information specified here is provided. This
will be brought up by Dick at next week s meeting.
5. CLASS, LIDB, 800/888, etc. are all included in the test plan. Once
the SPOC committee decides on the sequencing of tests it should
sufficiently meet this need.
6. Our target is better than 30 days, so meeting this should not be
problematic.
Agenda Item 3. NIIF update; review of test plan
Robin reported that NIIF is doing a cut-and-paste on the test plan and
pulling out interconnection pieces to work on. At the end of that
exercise they will take the inteconnect test plan and the ICC test plan
and keep it in their "living" document list. The first pass has started
and will conclude by the end of next week. Target initial availability
is August, final availability is
October.
Agenda Item 4. Operator Services (incl. LIDB)
This week, Carmen began testing various Operator Services/LIDB
scenarios. Essentially, an NPA NXX was opened for portability. Some test
calls were made (0+ dialed calls internal to the network). It worked
(call completed). Using access codes he tried other carriers networks
(AT&T-LD worked; MCI, Sprint failed). The failed problems were related
to gateway screening and those failures successfully completed after
some translations changes. There was some difficulty on some (maybe one)
carrier. This testing is continuing today and the current info is that
the sub-system code was placed in the called party address field and
troubleshooting is on-going. Queries came in and got out and clearly met
the two second time-out criteria. The real purpose of this testing is to
determine if the LIDB address has changed. Alternatively it is testing
the message relay function. This was characterized as regression
testing. Carmen pointed out that time permitting, additional testing
will continue.
Agenda Item 5. Test plan update (matrix)
The issue is what is the minimum set of tests that needs to be run.
Clearly it is dependent upon which services are offered by which
company. In addition, there may be a need to create a basic
feature-by-feature minimum set. Another alternative is to simply test
what can be tested and report on
those that are tested.
Walt pointed out that he selected a minimum set based on (1)what he
cannot run in his own lab and (2)what he would already have tested in
the trial [if the test was run once in the trial, it may not be
necessary to run with the next carrier]. Running 911 tests should happen
in all cases where it is appropriate (some areas may not have 911
features available).
SPOC group is working this issue
currently.
Agenda Item 6. Number pooling
ICC would like a number pooling (thousands group) plan in place by
August 1. We should be prepared to answer questions surrounding the
effect of number pooling on the existing test plan. Over the last two
days, the Operations group has concentrated on how the flows would
change. We should anticipate a request to test the network before
January 1.
Agenda Item 7. Next Meeting
Next meeting will be July 10 at 350 Orleans, Room 437. July 11 was set
aside for the SPOCs, but Dick will verify the date and find a room. Test
committee will then meet August 22 in Chicago. Perhaps conference calls
could be handled in between. September 11-12, 1997 set aside for
potential next meetings. Conference call for the test team will be on
July 24 1:00 to 3:00 PM CDT.