ICC Adhoc Test Committee Open Action Items:
Dated 06/05/97
Items closed 5/15/97 will be moved to closed list after June meeting.
------------------------------------------------------------
ISSUE #:006a
DATE OPENED: 08/26/96
DESCRIPTION: Want to include the NPAC test plan as an appendix to this
test plan.
RESPONSIBILITY: Barry Bishop, Operations Team will contact Donna
Navickas, NPAC team
DATE DUE: 01/06/97
DATE CLOSED:
STATUS: Open
08/26/96 - New Item
08/30/96 - Walt Subora and Barry Bishop will be meeting with the NPAC
team on Sep. 10 and/or 11 to talk about testing, schedules, etc. Will
bring back to this team.
12/11/96 - Discussion of how NPAC would be incorporated.
Most NPAC test plans are currently proprietary. Since they can't be
incorporated in the public test plan, a characterization of the coverage
is necessary in the master test plan, to show that it has been covered.
Sect 4.2.4 of test plan will have a matrix or summary which
characterizes the coverage. Then, at the conclusion of testing,
Lockheed would have to provide documentation of the test results.
01/09/97 - Lockheed will provide the final Turnup Test plan for the
addendum after it is final.
02/13/97 - NPAC committee is formally constructing this test plan and we
will get an update at the next meeting.
04/08/97 - Plan is just about complete. Submit section under final
review. Will get a status after next NPAC meeting. Perhaps a draft
tomorrow.
------------------------------------------------------------
ISSUE #:012
DATE OPENED: 10/18/96
DESCRIPTION: Need test scripts for Section 4.14 Choke Networks.
RESPONSIBILITY: Barry Bishop, AIT
DATE DUE: 11/04/96
DATE CLOSED:
STATUS: Open
10/18/96 - New Item
01/09/97 - Still on hold. These numbers are not portable. Providers will
have to hook up to tandem the same as we do to limit calls. Operations
open issue #41.
02/13/97 - Will keep in test plan but will not expand in the Illinois
forum for the MSA1 test. May need to expand when enter other MSA s.
03/11 - someone else in AIT??
04/08/97 - Still an open issue. Barry hopes to resolve in the next
couple of weeks.
05/15/97 - synonymous with mass calling - as soon as we get items from
the Operations team Walt will try to find someone at Ameritech to write
scripts.
------------------------------------------------------------
ISSUE #:018
DATE OPENED: 11/21/96
DESCRIPTION: Need an ANI failure test case for E911. 911 router will
look up default ESN per incoming trunk group.
RESPONSIBILITY: Nancy DeRoo, AIT
DATE DUE: 01/15/97
DATE CLOSED:
STATUS: Open
11/21/96 - New Item
01/09/97 - Nancy DeRoo is still working the issue. Due date changed to
01/15/97.
02/13/97 - Nancy gave to Walt Subora for inclusion in test plan. Walt
will send to Bill. Also, Rick, I-NENA, stated that this needs to be
tested as each new switch is turned up.
03/11/97 - Walt working to get in proper format.
04/08/97 - Nancy will redo after yesterday s meeting and Walt will
update. Get to Dick Dowd on Thursday, 4/10.
05/15/97 - items soon to be available for the test plan (probably by the
end of the month). Proposed web scripts will be on Barry s web page.
06/06/97 - These have been transmitted to Bill Belshaw and also are on
ported.com under the 911 team area.
------------------------------------------------------------
ISSUE #:024
DATE OPENED: 12/06/96
DESCRIPTION: Test team needs to determine failure scenario testing. IITP
tests will use a lab environment to run a broad range of failure
scenarios. How would this complement our efforts.
RESPONSIBILITY: : Team
DATE DUE: 02/11/97
DATE CLOSED:
STATUS: Open
12/06/96 - Walt will put on agenda for Dec. 11 meeting.
01/09/97 - Looping tests will be added to this section. Need to
investigate other scripts. Will see what NIIF (old IITP) can do that
will give confidence in June/July time frame.
03/11/97 - Joint meeting with SCP team on 04/08. Will try to cover
during this meeting.
04/08/97 - SCP team will submit to us some test scripts and Walt will
submit to NIIF/NT testing committee for inclusion.
05/15/97 - no change in status, although Walt gave an update on what the
NTC is looking at. He also highlighted some comparatively simple tests
in his lab and saw extensive looping. The currently implemented standard
is based on the XUDT message counts, which are not supported by anyone,
all use UDT messaging.
------------------------------------------------------------
ISSUE #:025
DATE OPENED: 12/06/96
DESCRIPTION: LEC-to-LEC interface tests are still not covered.
RESPONSIBILITY: All
DATE DUE: 02/13/97
DATE CLOSED:
STATUS: Open
12/06/95 - New item. Needs to have EDI interface firmed up
electronically. Also need tests for LEC to LEC interfaces when not EDI.
01/09/97 - To be provided by Operations team. Bill, MCI, will put
generic scripts in for the issue 1. Will be updated in next issue.
02/13/97 - Still open in Operations committee. These are pre-requisite
tests.
04/08/97 - Still open. Firmed up without Electronic interface on 4/10.
Operations team will work.
05/15/97 - Bill Belshaw is working on this. Update should come before
end of May.
------------------------------------------------------------
ISSUE #:026
DATE OPENED: 12/06/96
DESCRIPTION: Test scripts are needed for porting process flows.
RESPONSIBILITY: All
DATE DUE: ??
DATE CLOSED:
STATUS: Open
12/06/96 - Depends on getting better descriptions of the
process flows that will be used. Will definitely test whatever the
final flows are. Operations team has these flows in Flux right now.
12/11/96 - Bill Belshaw, MCI, added cases for operations. They are
generic. Will update when flows are firm.
01/09/97 - To be provided by Operations team. Will be updated in next
issue.
03/11/97 - changed to be "Porting process flows".
04/08/97 - Bill Belshaw, MCI, is working on these for section 4.4. Flows
will be finalized this week during the operations team meetings.
05/15/97 - Bill Belshaw is working on this. Text has been finalized and
approved. Update should come before end of May.
------------------------------------------------------------
ISSUE #:028
DATE OPENED: 12/11/96
DESCRIPTION: Need test cases for post dial delay tests.
RESPONSIBILITY: All
DATE DUE: 02/11/97
DATE CLOSED:
STATUS: Open
12/11/96 - Important to do something for post-dial delay, but this is a
very complex subject. It may be cause unnecessary confusion if the job
isn't done right. Will be discussed for issue 2.
01/09/97 - no update.
02/13/97 - Need to come up with a methodology for testing this for the
end user as well as for each of the test types, such as Operator
Services and TR1188 CNAM piece parts (measurements on each of the
queries, etc.). Ensure the call meets handoff criteria, etc.
03/11/97 - Metrics to be handled by SPoC subteam.
04/08/97 - Still open issue.
05/15/97 - post dial delay tests. Being worked by SPoC team. The
conclusion of the Operations team was to measure it and state the
results as fact, but make a judgment as to whether it is good or bad.
The responsibility is that each participating company report their post
dial delay under various scenarios. There is nothing that requires it to
be measured on EACH call. Dick pointed out that each participant is
being required to measure it and state the measurement method. Mitch
Kapor agreed to write a definition on PDD and give to Bill Belshaw
------------------------------------------------------------
ISSUE #:029
DATE OPENED: 12/11/96
DESCRIPTION: Need test cases for LSMS section.
RESPONSIBILITY: All
DATE DUE: 03/11/97
DATE CLOSED: 05/15/97
STATUS: CLOSED
12/11/96 - Needs to be covered in that area, too. FCC requires overall
characterization of all tests that have been done.
01/09/97 - No update.
02/13/97 - This is under the NPAC interface testing area. Bettie Shelby,
Worldcom, and Walt Subora, AIT, will write this section in generic terms
as to functionality s that might be needed outside of the NPAC interface
testing. Due date changed to 03/11/97.
03/11/97 - Walt to send to Bill what he and Bettie Shelby have come up
with.
04/09/97 - Gave to Bill today.
05/15/97 - Closed.
------------------------------------------------------------
ISSUE #:030
DATE OPENED: 12/11/96
DESCRIPTION: The SCP Subcommittee submitted a request for this group to
cover SCCP looping as part of the test plan.
RESPONSIBILITY: All
DATE DUE: 02/11/97
DATE CLOSED:
STATUS: Open
12/11/96 - Discussion on how to do this and for what scenarios. See
notes from Dec. 11 meeting. Need to get input from SCP team on schemes
to prevent/detect looping and how to implement for test purposes. Walt
will send out when available.
01/09/97 - Walt will try to include in January for issue 2 updates.
02/13/97 - Walt to take back to SCP committee for confirmation of what
they want included in test plan and when it will be available.
03/11/97 - Will try to cover in the joint SCP/Test team meeting on April
08, 1997.
04/08/97 - SCP team will submit a looping test and methodology to do it.
We will then consider it for the plan.
05/15/97 - SCP committee is submitting this next week. We will review at
next meeting.
------------------------------------------------------------
ISSUE #:032
DATE OPENED: 12/11/96
DESCRIPTION: Need to get a list of the NXXs and DNs for each company
that will be used for the inter-company test.
RESPONSIBILITY: All
DATE DUE: 01/07/97
DATE CLOSED:
STATUS: Open
12/11/96 - Need to get a list of the NXXs and DNs for each company. Send
them to Walt prior to January meeting. Minimum number of DNs per company
has not been decided. Crucially important to define clearly which NXXs
and DNs will be used, and to assure that only agreed-upon NXXs and DNs
are in the setup.
01/09/97 - NPA-NXXs were given by AT&T, AIT, MFS, and MCI at meeting
today. Need the info from TCG and Sprint. Also, need the LRNs and DPCs
for switches, actual DNs to be used, etc. Needed for the Feb. meeting.
02/13/97 - Walt will send out the Rate District list and it will be used
for input on the 02/27 conf. Call.
02/24/97 - Walt still does not have rate district list or proposed
offices.
03/11/97 - NXXs were submitted today and DNs will be on 3/21.
04/08/97 - Ameritech will send tomorrow. Others are in the last SPoC
meeting minutes. Will work at next SPoC meeting.
05/15/97 - Much of the data has been collected, the rest will be here
today and the issue should be closed tomorrow (assuming all info
arrives).
06/06/97 - NXXs and TNs were put forth. The actual porting partner s and
numbers to be ported will come out of the June 19 & 20th SPoC meetings.
------------------------------------------------------------
ISSUE #:034
DATE OPENED: 01/08/97
DESCRIPTION: Put picture reference in for each test case. And if no
picture available, draw new one. Submit to Mr. Bill by close of business
on Jan. 15, 1997. Policy is to submit reference or draw new picture when
submit test cases.
RESPONSIBILITY: ALL
DATE DUE: 01/15/97
DATE CLOSED:
STATUS: Open
01/09/97 - New item.
02/13/97 - Still waiting for some of the drawings (Mack Dobkins - ISDN,
Andy Chalk - non-conforming end office, Nancy DeRoo - 911).
03/11/97 - Walt has been able to convert Nancy DeRoo s 911 drawings and
will send them to Bill.
04/08/97 - Nancy s drawings have been given to Bill, along with the test
scripts. They are also on ported.com under the 911 area.
05/15/97 - Walt suggested closing this issue and leave it to those
running ISDN tests to draw out for their own purposes. Will leave open
until the June meeting.
------------------------------------------------------------
Issue #:044
DATE OPENED: 04/08/97
DESCRIPTION: SCP committee to write a one page looping test script
and submit it to the test committee.
RESPONSIBILITY: Wayne Heinmiller
DATE DUE: 05/15/97
DATE CLOSED: 05/15/97
STATUS: CLOSED
04/08/97 - New Issue.
05/15/97 - SCP looping test. This is a combination of other items and
Walt suggested that it be closed (due to redundancy).
------------------------------------------------------------
Issue #:045
DATE OPENED: 04/08/97
DESCRIPTION: Test team to figure out if, when and how to test
the looping test script submitted by the SCP committee.
RESPONSIBILITY: Walt Subora and ALL
DATE DUE: 05/15/97
DATE CLOSED: 05/15/97
STATUS: CLOSED
04/08/97 New Issue.
05/15/97 - looping test. It will be submitted but won t likely be
included in the trial. The NIIF will decide how to handle this on a
going forward basis. Walt suggested that this be closed.
------------------------------------------------------------
Issue #:046
DATE OPENED: 04/08/97
DESCRIPTION: Bill Belshaw to update Section 4.4
RESPONSIBILITY: Bill Belshaw
DATE DUE: 05/15/97
DATE CLOSED:
STATUS: Open
04/08/97 - New Issue.
05/15/97 - Bill is working to have updates by end of May.
------------------------------------------------------------
Issue #:047
DATE OPENED: 04/08/97
DESCRIPTION: Operations team needs to update section 4.3 for
cascading/rolling overloads.
RESPONSIBILITY: Barry Bishop
DATE DUE: 05/15/97
DATE CLOSED:
STATUS: Open
04/08/97 New Issue.
05/15/97 - This is of concern in a rolling overload situation. The text
in 4.3 will be updated to reflect this. Barry Bishop will be able to
discuss this later
------------------------------------------------------------
Issue #:048
DATE OPENED: 04/08/97
DESCRIPTION: Walt to talk with Jeff (972-519-3758) regarding whether
there is an issue with TTNs.
RESPONSIBILITY: Walt Subora
DATE DUE: 05/15/97
DATE CLOSED:
STATUS: Open
04/08/97 New Issue.
Is there an issue with TTNs? This is still open because Jeff and Walt
did not connect. It is possible that this will be discussed later today.
The real question is what activity is going on in T1S1 (per Jim
Joerger). Item remains open
------------------------------------------------------------
------------------------------------------------------------
ICC Adhoc Test Committee Closed Action Items:
Dated 05/08/97
------------------------------------------------------------
ISSUE #:001
DATE OPENED: 07/16/96
DESCRIPTION: Do we need to test NPA splits as part of field test?
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 01/06/97
DATE CLOSED: 04/08/97
STATUS: CLOSED
07/16/96 - New Item
08/26/96 - Walt Subora to take this to NPAC team and get input on mass
downloads, etc. for test cases.
01/09/97 - On hold, Barry Bishop will look into this. Operations team
open issue #15.
03/11/97 - Proposal to simulate during the NPAC turn-up testing and also
then do real Split testing in Detroit.
04/08/97 - Michigan inter-company committee is taking as an issue. Larry
Vasquez, Chairperson. Closed.
------------------------------------------------------------
ISSUE #: 002
DATE OPENED: 07/16/96
DESCRIPTION: Do we need to incorporate code sharing?
RESPONSIBILITY: Walt Subora, AIT
DUE DATE: 01/09/97
DATE CLOSED: 01/09/97
STATUS: CLOSED
07/16/96 - New Item
01/09/97 - Not different than we do today. Closed.
------------------------------------------------------------
ISSUE #:003
DATE OPENED: 07/16/96
DESCRIPTION: Need documents on web
RESPONSIBILITY: Walt Subora and Barry Bishop, AIT and Bill Belshaw, MCI
DATE DUE: 11/15/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
07/16/96 - New Item
09/17/96 - www.cameos.com/lnp MCI s website for current test plan.
10/18/96 - Barry Bishop's web site is www.ported.com. These notes will
be posted there in Word6 format. Open question whether the draft test
plan can reside there.
01/09/97 - See above. Documents on the Web. CLOSED.
------------------------------------------------------------
ISSUE #:004
DATE OPENED: 07/16/96
DESCRIPTION: Need input from NPAC team for section 2.
RESPONSIBILITY: Steve Markowski, Lockheed
DATE DUE: 01/27/97
DATE CLOSED: 02/13/97
STATUS: Closed
07/16/96 - New Item
01/09/97 - Received information from Lockheed for the NPAC as a summary
for section 4. We need names, telephone numbers, etc. for the contact
list in Section 2 as well as the Turnup Test Plan to put in the addendum
for reference. Steve will get to us the Section 2 info by next meeting
and the test plan when it is final.
02/13/97 - Closed
------------------------------------------------------------
ISSUE #:005
DATE OPENED: 07/16/96
DESCRIPTION: What is process for issues identification and resolution?
Could we use the web pages for input and status?
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 02/11/97
DATE CLOSED: 02/13/97
STATUS: Closed
07/16/96 - New Item
01/09/97 - Put into words in the issue 1 test plan and change after
issue 1 is final and process is provided.
02/13/97 - Closed.
------------------------------------------------------------
ISSUE #:006
DATE OPENED: 08/26/96
DESCRIPTION: Need the NPAC committee to determine the test schedule and
provide for inclusion in our test plan.
RESPONSIBILITY: Steve Markowski, Lockheed
DATE DUE: 01/06/97
DATE CLOSED: 02/13/97
STATUS: Closed
08/26/96 - New Item
09/17/96 - Walt has done this. A meeting is scheduled on Oct.02, 1996
with NPAC about testing. The schedule, assumptions and terms are
attached to the Sep 17, 1996 notes. (Attachment 2 of that output)
11/21/96 - NPAC overall schedule was presented by Walt Subora from NPAC
committee output. Still need to determine affect on our test interval.
See notes from Nov. 21 meeting.
12/11/96 - Lockheed provided an overview of a schedule, with three
locations, that brought only certified carriers and live data into the
NPAC after May 05, 1997. This would indeed allow for a start in June as
test data would not be flowing into live LSMSs and SCPs. See notes from
Dec. 11 meeting.
01/09/97 - Steve and Donna Navickas provided new dates which still
provide for the start of inter-company testing on 06/15/97. Will keep
open until final schedule is put together.
02/13/97 - Closed. Will manage now as part of the overall test schedule.
------------------------------------------------------------
ISSUE #:007
DATE OPENED: 09/17/96
DESCRIPTION: Do we want to test conversion from interim portability to
true LRN portability?
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 01/06/97
DATE CLOSED: 03/11/97
STATUS: Closed
09/17/96 - New Item. Tabled for the present as a future issue.
01/09/97 - This should be handled in inter-company interconnection
agreements and not part of this test plan.
02/13/97 - Operations committee has not come to consensus on this issue.
Still open.
03/11/97 - Closed for now. Operations team has withdrawn this issue.
------------------------------------------------------------
ISSUE #:008
DATE OPENED: 09/17/96
DESCRIPTION: What is the definition of qualification tests for a
newcomer LNP SP (Service Provider)?
RESPONSIBILITY: All
DATE DUE: 02/28/97
DATE CLOSED: 04/09/97
STATUS: CLOSED
09/17/96 - New Issue
01/07/97 - We will select a set as part of the test plan and submit to
the Operations committee by March meeting.
02/13/97 - Bettie Shelby, Steve Markowski and Dick Dowd will work this
issue. They will draft their thoughts on this and present at this
committee at the March meeting.
03/11/97 - SP to SP testing will be handled by the NIIF (Robin s group).
NPAC is currently not part of that.
04/08/97 - NIIF will take the complete test plan and change name in
entirety. Will also take a sub set for interconnection test for inter SP
testing. Another meeting 4/24-25 about the test plan.
04/09/97 - Jim Joerger comments: SP to SP testing for a new entrant is
covered in Section 3 of the test plan as part of the prerequisite
activities. SP to SP interconnection testing is covered in the Appendix
as a reference and is also included as part of the NIIF test procedures
for interconnection for LNP. New entrant LNP SPs would also have to show
NPAC certification as part of the prerequisites to participate in
testing. The test plan will be turned over to the NIIF after 09/26/97
test completion. Item Closed.
------------------------------------------------------------
ISSUE #:009
DATE OPENED: 10/18/96
DESCRIPTION: AT&T will provide drafts of IXC and LSP sections under 4.5
by 10/28 to allow review time before 11/4 conference call. It will be
somewhat compacted in relation to the plan reviewed today.
RESPONSIBILITY: Mitch Fuchs and OC Jackson, AT&T
DATE DUE: 11/04/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
10/18/96 - New Item
01/09/97 - The submission was accepted in December. Need drawing
references. See AI#034.
------------------------------------------------------------
ISSUE #:009a
DATE OPENED: 11/04/96
DESCRIPTION: Need coverage matrices for AT&T provided sections
RESPONSIBILITY: Mitch Fuchs and OC Jackson, AT&T
DATE DUE: 11/14/96
DATE CLOSED:
STATUS: CLOSED
11/04/96 - Mitch will produce a coverage matrix for local & intra-LATA
calls. OC. will produce a coverage matrix for inter-LATA calls. Edits
from Mitch Fuchs and OC Jackson to Bill Belshaw by start of day on
11/14, for discussion at 11/21 meeting.
01/09/97 - The submission was accepted in December. Need drawing
references. See AI#034.
------------------------------------------------------------
ISSUE #:010
DATE OPENED: 10/18/96
DESCRIPTION: - Walt requests draft test plan contributions in Word 6.0
format on floppy disk, direct to Bill and direct to Walt for Issue 01 of
document.
RESPONSIBILITY: ALL
DATE DUE: 11/14/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
10/18/96 - New Item
11/21/96 - Sections were sent to Walt and Bill. Will be included in
December review of document.
01/09/97 - Changes and new scripts were submitted. Included in test
plan. Need drawing references. See AI #034.
------------------------------------------------------------
ISSUE #:011
DATE OPENED: 10/18/96
DESCRIPTION: Need test scripts for section 4.13 Code Gapping.
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 11/04/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
10/18/96 - New Item
01/09/97 - Scripts were submitted and accepted in December. Need drawing
references. See AI #034.
------------------------------------------------------------
ISSUE #:013
DATE OPENED: 10/18/96
DESCRIPTION: Need test scripts for Section 4.8 Operator & Coin.
RESPONSIBILITY: OC Jackson, AT&T and Carmen Colella, AIT
DATE DUE: 12/11/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
10/18/96 - New Item
11/21/96 - Mitch Bilder, AT&T has a section for Operator and Coin test
cases. Needs to be reviewed. Has much to do with IXC Operator Calls.
Will be delivered to AIT by Ralph Brown, AT&T. Walt will include it on
www.ported.com.
11/21/96 - Carmen Colella, AIT gave a presentation on Operator test
cases needed for local Operators. He will flesh out required cases and
work with Ed Hendrix, BellSouth and Mitch Bilder, AT&T to update this
section.
12/06/96 - Carmen is assembling a matrix of orig. number, called number,
billing number for review at meeting. Bill offers to add it to the
matrix section of the test plan.
12/11/96 - Handout from Carmen Colella, AIT. Asking for tests from
every network that will use the Ameritech LIDB. Since a collect or
third-party-billed call can come from anywhere, the LIDB queries will go
to and from all possible networks. This leads to national compatibility
issues.
Carmen suggested a separate committee for testing of operator services.
There was a requirements OS subgroup. They would be a logical place to
start to constitute such a committee. Barry will check with operations
team to get some names. Could include SMEs from other than the direct
participants on this committee.
01/09/97 - The submission by AT&T is accepted as the Operator Services
section 4.8. Carmen is working on total list of tests for the addendum.
Carmen will hold a meeting with appropriate SMEs from other companies to
determine over all Operator Services test schedule, especially,
validation queries. New item for this. CLOSED.
------------------------------------------------------------
ISSUE #:014
DATE OPENED: 10/18/96
DESCRIPTION: Need test scripts for Section 4.6.3 Voice Mail.
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 11/21/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
10/18/96 - New Item
01/09/97 - Scripts submitted in December and accepted. Need drawing
references. See AI #034.
------------------------------------------------------------
ISSUE #:015
DATE OPENED: 11/21/96
DESCRIPTION: How will calls from law enforcement agencies (not PSAPs) be
referred to the correct telco.
RESPONSIBILITY: Barry Bishop, Operations team.
DATE DUE: 01/29/97
DATE CLOSED: 04/08/97
STATUS: CLOSED
11/21/96 - New Issue
01/09/97 - Will be handled by 9-1-1 meeting on 01/29/97. See operation
team notes from 01/07/97 meeting.
02/13/97 - Still under the Operations committee. Open an issue with
Barry .
03/11/97 - referred to the 911 Adhoc team.
04/08/97 - Move from here to 911 team. Closed.
------------------------------------------------------------
ISSUE #:016
DATE OPENED: 11/21/96
DESCRIPTION: Need callbacks from 911 bureaus in the test plan. Need to
add a return call to each test case.
RESPONSIBILITY: Mitch Fuchs, AT&T
DATE DUE: 12/11/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
11/21/96 - New Item
01/09/97 - Mitch Fuchs submitted updated scripts in December. Still need
drawings references. Se AI #034.
------------------------------------------------------------
ISSUE #:017
DATE OPENED: 11/21/96
DESCRIPTION: Tough scenario: 911 arrangement with Ameritech, but ported
number is in a Sprint-Centel serving area. Will have to do
router-to-router (tandem-to-tandem) routing of traffic.
RESPONSIBILITY: Nancy DeRoo, AIT and Andy Chalk, Sprint-Centel.
DATE DUE: 02/11/97
DATE CLOSED: 03/11/97
STATUS: CLOSED
11/21/96 - New Item
01/09/97 - Nancy DeRoo is still working the issue. Due date changed to
02/11/97.
02/13/97 - Sprint-Centel states this is under standard interconnection
agreements to build router trunks to the Sprint routers. If Ameritech
wants to interconnect to Sprint-Centel, they should enter into an
agreement. I will take to Nancy for full closure.
03/11/97 - closed
------------------------------------------------------------
ISSUE #:019
DATE OPENED: 11/21/96
DESCRIPTION: Need the Operator Services schedule for V.O. software and
IWS positions from Ameritech.
RESPONSIBILITY: Carmen Colella, AIT
DATE DUE: 01/06/97
DATE CLOSED: 02/13/97
STATUS: Closed
11/21/96 - New Item
01/09/97 - Official VO date is 07/19/97. NORTEL still working out which
office is the VO site. Ameritech still believes this will be in MSA-1.
02/13/97 - Nortel will have software in Wabash July 17 and Willowcrest
July 30. Closed.
------------------------------------------------------------
ISSUE #:020
DATE OPENED: 11/21/96
DESCRIPTION: What is the availability requirement on backup NPAC?? How
soon would it have to come on-line after a primary NPAC failure.
RESPONSIBILITY: : Walt Subora, AIT and Donna Navickas, NPAC chair
DATE DUE: 02/11/97
DATE CLOSED: 02/13/97
STATUS: Closed
11/21/96 - New Item. Walt will take to the NPAC committee.
01/09/97 - Steve, Lockheed, stated that there are no scheduled switches
between primary and backup except for software updates. He stated that
primary and secondary are always active and switch is basically from
LSMS to NPAC re-homing of links and not NPAC actual switch. Stated that
Re-sync back is not trivial. Barry suggested that some type of yearly
switch for assurance purposes may be needed. Steve to address. New due
date of 02/11/97.
02/13/97 - Steve Markowski, Lockheed, stated that a routine schedule
will be established for backup and recovery testing. It will be tested
in initial deployment and when Software Upgrade 2 comes in October.
Schedule will be established later, but will be based upon Software
upgrades, etc. Closed.
------------------------------------------------------------
ISSUE #:021
DATE OPENED: 10/18/96
DESCRIPTION: Need to determine test schedule for inter-company test.
Operations team needs by Dec. 01.
RESPONSIBILITY: : Walt Subora, AIT and Donna Navickas, NPAC chair
DATE DUE: 12/01/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
10/18/96 - New item.
11/21/96 - Came to preliminary consensus that testing could be done
after the NPAC finished, starting Jul. 01, 1997 and finishing by Aug.
15, 1997 with straggler testing/fixes after that. Will give to
Operations team. Need to confirm schedule with them and NPAC committee.
01/07/97 - Test schedule was determined and submitted to Operations
committee. See notes from November and December test team meetings.
------------------------------------------------------------
ISSUE #:022
DATE OPENED: 10/18/96
DESCRIPTION: Need to determine final test schedule for inter-company
test.
RESPONSIBILITY: : Walt Subora, AIT and Donna Navickas, NPAC chair
DATE DUE: 02/11/97
DATE CLOSED: 03/11/97
STATUS: CLOSED
10/18/96 - New Item
01/09/97 - Still working the issues with Lockheed, but still on track to
start inter-company test on 06/15/97.
02/13/97 - New dates are 07/24/97 to start.
03/11/97 - closed
------------------------------------------------------------
ISSUE #:023
DATE OPENED: 11/04/96
DESCRIPTION: Test team needs to come up with a definition and job
description for inter-company test coordinator to ensure all parts of
the implementation come together, including the NPAC piece.
RESPONSIBILITY: : Walt Subora, AIT and Bill Belshaw, MCI
DATE DUE: 12/01/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
11/04/96 - Bill suggested that Barry Bishop, Operations Chair, send an
e-mail to Dick Dowd s, MCI, boss and ask if Dick could write the
description as he performed the job for the New York Portability trial.
Barry said he would.
11/21/96 - Barry has sent the E-mail. Waiting for Dick to respond.
12/06/96 - Dick Dowd, MCI, responded with a job description and
volunteered to be the coordinator. Barry Bishop will take back to the
Steering Committee for discussion and approval. AT&T had also
volunteered to be coordinator.
12/11/96 - Barry stated that the Steering Committee had agreed and
accepted Dick Dowd, MCI, as the inter-company test coordinator. The test
team unanimously agreed.
01/09/97 - Dick Dowd is the test coordinator. CLOSED.
------------------------------------------------------------
ISSUE #:027
DATE OPENED: 12/11/96
DESCRIPTION: Need test scripts for Section 4.5.8 AIN interactions with
LNP.
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 12/24/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
12/11/96 - New Item
12/23/96 - AIN test scripts shipped to Bill on Diskette.
01/09/97 - Accepted. Need drawing references. See AI #034.
------------------------------------------------------------
ISSUE #:031
DATE OPENED: 12/11/96
DESCRIPTION: Need each test plan writer reference the appropriate
figures in Appendix A for each test case.
RESPONSIBILITY: All
DATE DUE: 12/24/96
DATE CLOSED: 01/09/97
STATUS: CLOSED
12/11/96 - Due with the updates to the test scripts for issue 1.
01/09/97 - References and new drawings were submitted to Bill for some
of the areas. Still need from others. Will be tracked by AI #034.
------------------------------------------------------------
ISSUE #:033
DATE OPENED: 01/08/97
DESCRIPTION: Barry to take back to switch requirements team to add
requirement to have the switches mark the ported out numbers as ported
out, not vacant. This could affect the 911 databases if this number is
reassigned by the owner SP after ported out to another SP.
RESPONSIBILITY: Barry Bishop, Operations team
DATE DUE: 02/11/97
DATE CLOSED: 03/11/97
STATUS: CLOSED
01/09/97 - New item.
02/13/97 - It is up to each SP to ensure they do not reassign a ported
number within their own network.
03/11/97 - closed
------------------------------------------------------------
ISSUE #:035
DATE OPENED: 01/08/97
DESCRIPTION: Need some kind of on-going switch over testing from NPAC
for switch to backup NPAC. Will do a scheduled outage during switch
software upgrades, etc. (phase 2)
RESPONSIBILITY: Steve Markowski, Lockheed
DATE DUE: 02/28/97
DATE CLOSED: 02/13/97
STATUS: Closed
01/09/97 - New item.
02/13/97 - This is redundant with Item 20. Closed.
------------------------------------------------------------
ISSUE #:036
DATE OPENED: 01/08/97
DESCRIPTION: DeRoo question - can the number in the switch give
indication that the number is ported. Answer - Only EWSD has this
capability now. Will not be used. Barry will check into the possibility
of other vendors giving the capability.
RESPONSIBILITY: Barry Bishop, Operation team
DATE DUE: 02/11/97
DATE CLOSED: 02/13/97
STATUS: Closed
01/09/97 - New item.
02/13/97 - Closed as redundant with item 33.
------------------------------------------------------------
ISSUE #:037
DATE OPENED: 01/08/97
DESCRIPTION: Question: Some SPs do not want to do GTTs for open NPA-NXXs
unless they actually port numbers from the NPA-NXXs. There was much
discussion. This is given to the Operations team for
resolution/guidelines.
RESPONSIBILITY: Barry Bishop, Operation team
DATE DUE: 02/11/97
DATE CLOSED: 03/17/97
STATUS: CLOSED
01/09/97 - New item.
02/13/97 - Walt will open with Barry for Operations team to consider.
03/11/97 - Walt has asked the Operations team for an update.
03/17/97 - Per Barry Bishop, this has been withdrawn by Sprint as an
issue. Closed.
------------------------------------------------------------
ISSUE #:038
DATE OPENED: 01/08/97
DESCRIPTION: Question about later comers - how late can they start.
Suggested must be completed by 6-15 or would have to wait until 7-4.
Still under consideration. Barry and Donna will take back to the
Operations committee.
RESPONSIBILITY: Barry Bishop, Operation team
DATE DUE: 02/11/97
DATE CLOSED: 04/08/97
STATUS: Closed
01/09/97 - New item.
02/13/97 - There was another slip in NPAC schedule. The test bed new
date needs to be provided by NPAC. This issue is related to issue #8.
03/11/97 - Much discussion on this. As they NPAC testing schedule will
be adhered to by WorldCom, it was decided to let them start on/about
Aug. 15 and include tests for bringing up a new SP on line. Other SPs
that have not been able to start by now are not part of the Illinois FCC
Field Test.
04/08/97 - Spoc s will work the issues of what tests need to be
executed. Ed Elkin pointed out that Sections 4.1 - 4.3 could be tested
by WorldCom prior to the 08/15 start date. Closed.
------------------------------------------------------------
ISSUE #:039
DATE OPENED: 01/08/97
DESCRIPTION: Need PSAPs by office for inter-company test.
RESPONSIBILITY: Nancy DeRoo, AIT, INENA
DATE DUE: 02/11/97
DATE CLOSED: 04/08/97
STATUS: Closed
01/09/97 - New item.
02/13/97 - Rick Jones, want to do actual tests when NXXs are known. Also
to target PSAPs for testing when porting numbers.
03/11/97 - As the NXXs are now known, Bob Bartenstein, AIT SPoC, will
pursue with Nancy DeRoo for the PSAPs and their offices.
04/08/97 - Closed. Sent to Dick.
------------------------------------------------------------
Issue #:040
DATE OPENED: 02/13/97
DESCRIPTION: Walt to get out Rate District list to each SP.
RESPONSIBILITY: Walt Subora, AIT
DATE DUE: 02/20/97
DATE CLOSED: 03/11/97
STATUS: CLOSED
02/13/97 - New item.
02/24/97 - Walt still does not have rate district list or proposed
offices.
03/11/97 - As the NPA/NXXs have been worked out as well as the rate
Districts for the Field Trial, this is now a mute point. The NPA/NXXs
were picked for this test were picked using the Tariffs and the LERG.
Closed
------------------------------------------------------------
Issue #:041
DATE OPENED: 02/13/97
DESCRIPTION: Each SP to look at rate district list to see if we can come
up with a better coverage map for the inter-company test..
RESPONSIBILITY: ALL
DATE DUE: 03/11/97
DATE CLOSED: 04/08/97
STATUS: CLOSED
02/13/97 - New item.
03/11/97 - This is on the Conf. Call agenda for Mar. 21. We will close
after the call is all is available.
04/08/97 - Closed.
------------------------------------------------------------
Issue #:042
DATE OPENED: 02/13/97
DESCRIPTION: Need to put together inter-company trunking arrangements
for the test scenarios.
RESPONSIBILITY: ALL
DATE DUE: 03/11/97
DATE CLOSED: 04/08/97
STATUS: CLOSED
02/13/97 - New item.
Andy Chalk asked if AIT would allow routing through our tandem to
another SP, if direct trunks cannot be put into place for the
inter-company test time frame?
03/11/97 - Will work aggressively during the April meetings. SPs should
come with Office CLLIs, Point Codes (STPs, SSPs, SCPs?), Trunk Groups
already in place, Tandem s that are interconnected, etc.
04/08/97 - Will be worked by the SpoC committee. Meeting notes will be
on www.ported.com. Closed.
------------------------------------------------------------
Issue #:043
DATE OPENED: 03/11/97
DESCRIPTION: WorldCom needs to confirm 08/15 start date.
RESPONSIBILITY: Betty Shelby and Dick Anderson
DATE DUE: 04/09/97
DATE CLOSED: 04/08/97
STATUS: CLOSED
03/11/97 - New Issue.
04/08/97 - Bettie Shelby stated it is firm. Closed.
------------------------------------------------------------