| ID |
Name |
Duration |
Start |
Finish |
Actual Start |
Actual Finish |
Resource Names |
| 1 | Initial LNP Implementation (all) | 774.00d | 9/23/96 | 9/9/99 | NA | NA | |
| 2 | __1.0 NPAC SMS SYSTEM DEVELOPMENT | 774.00d | 9/23/96 | 9/9/99 | NA | NA | |
| 3 | ____1.1 Functional Requirements Definition and Verification | 35.00d | 12/31/96 | 2/17/97 | NA | NA | |
| 4 | ______1.1.1 Committee Sign off on Revised Requirements | 0.00d | 12/31/96 | 12/31/96 | NA | NA | |
| 5 | ______1.1.2 Ship Revised FRS Version 1.3 | 5.00d | 1/6/97 | 1/10/97 | NA | NA | |
| 6 | ______1.1.3 Industry Review of Final FRS Version 1.3 | 14.00d | 1/13/97 | 1/30/97 | NA | NA | |
| 7 | ______1.1.4 Industry Review of NANC SF Changes | 5.00d | 1/27/97 | 1/31/97 | NA | NA | |
| 8 | ______1.1.5 Illinois sign-off on NANC SF Changes | 1.00d | 2/5/97 | 2/5/97 | NA | NA | |
| 9 | ______1.1.6 Publish FRS Version 1.4 (NANC SF Changes) | 1.00d | 2/17/97 | 2/17/97 | NA | NA | |
| 10 | ____2.0 IIS Revision | 49.00d | 12/31/96 | 3/7/97 | NA | NA | |
| 11 | ______2.1 Committee Sign off on Revised Flows | 0.00d | 12/31/96 | 12/31/96 | NA | NA | |
| 12 | ______2.2 Ship Revised IIS Version 1.3 | 0.00d | 2/7/97 | 2/7/97 | NA | NA | |
| 13 | ______2.3 Industry Review of Final IIS Version 1.3 | 14.00d | 2/12/97 | 3/3/97 | NA | NA | |
| 14 | ______2.4 Revised ASN.1 Released (IIS V1.4) | 27.00d | 1/2/97 | 2/7/97 | NA | NA | |
| 15 | ______2.5 Revised GDMO Released (IIS V1.4) | 27.00d | 1/2/97 | 2/7/97 | NA | NA | |
| 16 | ______2.6 Publish IIS Version 1.4 | 1.00d | 2/7/97 | 2/7/97 | NA | NA | |
| 17 | ______2.7 Committee Sign off on NANC SF Changes | 1.00d | 1/31/97 | 1/31/97 | NA | NA | |
| 18 | ______2.8 Revised ASN.1 Released (IIS V1.5) | 1.00d | 2/27/97 | 2/27/97 | NA | NA | |
| 19 | ______2.9 Revised GDMO Released (IIS V1.5) | 1.00d | 2/27/97 | 2/27/97 | NA | NA | |
| 20 | ______2.10 Publish IIS Version 1.5 | 1.00d | 3/7/97 | 3/7/97 | NA | NA | |
| 21 | ____2.1 Ship Updated External Design | 0.00d | 1/10/97 | 1/10/97 | NA | NA | |
| 22 | ____2.1.1 Ship External Design update | 1.00d | 2/18/97 | 2/18/97 | NA | NA | |
| 23 | ____3.0 Coding and Unit Testing | 106.00d | 9/23/96 | 2/17/97 | NA | NA | |
| 24 | ______3.2 Perform Unit Code and Test | 44.00d | 9/23/96 | 11/21/96 | NA | NA | |
| 25 | ______3.2 Complete Intitial Unit Code and Test | 1.00d | 12/23/96 | 12/23/96 | NA | NA | |
| 26 | ______3.3 Perform Unit Code and Test for Process Revision | 11.00d | 1/16/97 | 1/30/97 | NA | NA | |
| 27 | ______3.4 Perform Unit Code and Test for new NANC flow | 11.00d | 2/3/97 | 2/17/97 | NA | NA | |
| 28 | ____4.0 Communications | 704.00d | 12/30/96 | 9/9/99 | NA | NA | |
| 29 | ______4.1 Install and Test Circuits | 72.00d | 12/30/96 | 4/8/97 | NA | NA | |
| 30 | ______4.1.1 Ameritech | 72.00d | 12/30/96 | 4/8/97 | NA | NA | |
| 31 | ______4.1.2 AT&T | 45.00d | 12/30/96 | 2/28/97 | NA | NA | |
| 32 | ______4.1.3 MCI | 72.00d | 12/30/96 | 4/8/97 | NA | NA | |
| 33 | ______4.1.4 Worldcom | 72.00d | 12/30/96 | 4/8/97 | NA | NA | |
| 34 | ______4.1.5 ILEC 1 | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 35 | ______4.1.6 ILEC XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 36 | ______4.2 Provision Communications Infrastruture | 15.00d | 4/9/97 | 4/29/97 | NA | NA | |
| 37 | ______4.3 Test Communications Infrastructure (WAN & LAN) | 9.00d | 4/30/97 | 5/12/97 | NA | NA | |
| 38 | ____5.0 Test Plan Development | 165.00d | 10/1/96 | 5/19/97 | NA | NA | |
| 39 | ______5.1 Interoperability Test Plan Development V1.1 | 63.00d | 11/20/96 | 2/14/97 | NA | NA | |
| 40 | ______5.2 Develop IIP S2S Test Plan | 30.00d | 10/7/96 | 11/15/96 | NA | NA | |
| 41 | ______5.3 Develop IIP MO Test Plan | 66.00d | 10/7/96 | 1/6/97 | NA | NA | |
| 42 | ______5.4 Develop IIP AP2AP Test Plan | 102.00d | 10/7/96 | 2/25/97 | NA | NA | |
| 43 | ______5.5 Review IIP Test Plan | 77.00d | 11/15/96 | 3/3/97 | NA | NA | |
| 44 | ______5.6 NIVT Development | 141.00d | 10/1/96 | 4/15/97 | NA | NA | |
| 45 | ______5.7 NIVT Draft First Release | 0.00d | 2/20/97 | 2/20/97 | NA | NA | |
| 46 | ______5.7.1 NIVT Draft Second Release | 0.00d | 3/20/97 | 3/20/97 | NA | NA | |
| 47 | ______5.7.2 NIVT Final Release | 0.00d | 4/15/97 | 4/15/97 | NA | NA | |
| 48 | ______5.8 Turn-Up Test Plan Development | 127.00d | 11/22/96 | 5/19/97 | NA | NA | |
| 49 | ____5.9 Testing | 730.00d | 11/22/96 | 9/9/99 | NA | NA | |
| 50 | ______6.0 LSP Interoperability Testing | 730.00d | 11/22/96 | 9/9/99 | NA | NA | |
| 51 | ________6.1 Perform S2S | 730.00d | 11/22/96 | 9/9/99 | NA | NA | |
| 52 | __________6.1.1 Ameritech | 2.00d | 1/13/97 | 1/14/97 | NA | NA | |
| 53 | __________6.1.2 AT&T | 2.00d | 11/22/96 | 11/25/96 | NA | NA | |
| 54 | __________6.1.3 MCI | 2.00d | 2/10/97 | 2/11/97 | NA | NA | |
| 55 | __________6.1.4 WorldCom | 2.00d | 2/10/97 | 2/11/97 | NA | NA | |
| 56 | __________6.1.5 ILEC 1 | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 57 | __________6.1.6 ILEC XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 58 | ________6.2 Perform MO | 672.00d | 2/12/97 | 9/9/99 | NA | NA | |
| 59 | __________6.2.1 Ameritech | 5.00d | 3/27/97 | 4/2/97 | NA | NA | |
| 60 | __________6.2.2 AT&T | 5.00d | 3/27/97 | 4/2/97 | NA | NA | |
| 61 | __________6.2.3 MCI | 5.00d | 2/12/97 | 2/18/97 | NA | NA | |
| 62 | __________6.2.4 WorldCom | 15.00d | 3/27/97 | 4/16/97 | NA | NA | |
| 63 | __________6.2.5 ILEC1 | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 64 | __________6.2.6 ILEC XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 65 | ________6.3 Perform AP2AP | 667.00d | 2/19/97 | 9/9/99 | NA | NA | |
| 66 | __________6.3.1 Ameritech | 18.00d | 4/16/97 | 5/9/97 | NA | NA | |
| 67 | __________6.3.2 AT&T | 18.00d | 4/16/97 | 5/9/97 | NA | NA | |
| 68 | __________6.3.3 MCI | 18.00d | 2/19/97 | 3/14/97 | NA | NA | |
| 69 | __________6.3.4 Worldcom | 18.00d | 4/16/97 | 5/9/97 | NA | NA | |
| 70 | __________6.3.5 ILEC 1 | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 71 | __________6.3.6 ILEC XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 72 | ________6.4 Complete LSP Interoperability Testing | 0.00d | 6/30/97 | 6/30/97 | NA | NA | |
| 73 | ______7.0 NIVT Testing | 20.00d | 4/15/97 | 5/12/97 | NA | NA | |
| 74 | ________7.1 Perform Software Acceptance Testing | 20.00d | 4/15/97 | 5/12/97 | NA | NA | |
| 75 | ________7.2 NPAC/SMS Final Release 1.0 | 0.00d | 5/12/97 | 5/12/97 | NA | NA | |
| 76 | ______8.0 LSP Turnup Testing | 42.00d | 5/13/97 | 7/9/97 | NA | NA | |
| 77 | ______8.1 Database Clean Up & FCC Trial Grooming | 10.00d | 7/9/97 | 7/22/97 | NA | NA | |
| 78 | ______8.2 Conduct FCC Field Trial | 47.00d | 7/24/97 | 9/26/97 | NA | NA | |
| 79 | ____9.0 LSP USER AND NPAC OPERATIONS TRAINING | 118.00d | 11/1/96 | 4/15/97 | NA | NA | |
| 80 | ______9.1 Develop LSP User and NPAC Operations Training Materials | 118.00d | 11/1/96 | 4/15/97 | NA | NA | |
| 81 | ______9.2 Conduct LSP User Training | 0.00d | 4/15/97 | 4/15/97 | NA | NA | |
| 82 | ____10.0 NPAC Operations | 61.00d | 2/14/97 | 5/12/97 | NA | NA | |
| 83 | ______10.1 Draft M&P Document | 0.00d | 2/14/97 | 2/14/97 | NA | NA | |
| 84 | ______10.2 Final Draft M&P Document | 0.00d | 5/12/97 | 5/12/97 | NA | NA | |
| 85 | ____11.0 FULL OPERATIONS | 0.00d | 9/29/97 | 9/29/97 | NA | NA | |
| 87 | __New TC NPAC Schedule | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 88 | ____ILEC xx Schedule appropriate NPAC testing, etc | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 90 | __Order Interface Testing (Electronic and/or Manual) | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 91 | ____ILEC Test Order Interfaces as appropriate | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 93 | __End Office Preparation | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 94 | ____Ameritech Switch type(s) (Same as Illinois) | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 95 | ____Lab Testing (Same as Illinois) | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 96 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 98 | ____AT&T Switch type XXX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 99 | ____Lab Testing (if necessary) TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 100 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 102 | ____MCI Metro Switch type XXX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 103 | ____Lab Testing (if necessary) TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 104 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 106 | ____WorldCom Switch type XXX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 107 | ____Lab Testing (if necessary) TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 108 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 110 | ____Other ILEC Switch type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 111 | ____Lab Testing (if necessary) TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 112 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 114 | __Operator Services Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 115 | ____Ameritech Operator Services Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 116 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 117 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 118 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 120 | ____AT&T Operator Services Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 121 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 122 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 123 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 125 | ____MCI Operator Services Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 126 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 127 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 128 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 130 | ____WorldCom Operator Services Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 131 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 132 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 133 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 135 | ____Other ILEC Operator Services Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 136 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 137 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 138 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 140 | __IXC Platforms | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 141 | ____AT&T IXC Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 142 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 143 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 144 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 146 | ____GTE IXC Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 147 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 148 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 149 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 151 | ____MCI IXC Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 152 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 153 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 154 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 156 | ____Sprint IXC Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 157 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 158 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 159 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 161 | ____WorldCom IXC Platform | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 162 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 163 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 164 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 166 | ____Other IXC Platform(s) | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 167 | ____Office Type(s) XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 168 | ____Lab testing TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 169 | ____Test Town TBD | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 171 | __Inter-Company Testing | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 172 | ____Decide What Tests are Mandatory | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 173 | ____Insert Tasks | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 174 | ____Insert Tasks | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 175 | ____Insert Tasks | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 176 | ____Insert Tasks | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 177 | ____Insert Tasks | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 179 | __Minneapolis MSA "Ready to Port" dates | 419.00d | 2/2/98 | 9/9/99 | NA | NA | |
| 180 | ____Ameritech | 1.00d | 2/2/98 | 2/2/98 | NA | NA | |
| 181 | ______ELWOWI11RS0 | 1.00d | 2/2/98 | 2/2/98 | NA | NA | |
| 182 | ______HDSNWI01DS0 | 1.00d | 2/2/98 | 2/2/98 | NA | NA | |
| 183 | ______HLTNWI11RS1 | 1.00d | 2/2/98 | 2/2/98 | NA | NA | |
| 184 | ______RBRTWI11RS1 | 1.00d | 2/2/98 | 2/2/98 | NA | NA | |
| 185 | ______RVFLWI11DS0 | 1.00d | 2/2/98 | 2/2/98 | NA | NA | |
| 187 | ____AT&T | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 188 | ______Office XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 189 | ______Office XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 191 | ____MCI | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 192 | ______Office XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 193 | ______Office xx | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 195 | ____World Com | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 196 | ______Office XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 197 | ______Office xx | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 199 | ____ILEC XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 200 | ______Office XX | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |
| 201 | ______Office xx | 1.00d | 9/9/99 | 9/9/99 | NA | NA | |