All,

These are corrections to the July 24 meeting minutes, specifically

Action Item 24. Joe Questore will help Walt write the letter to the NTC,

not be the receipient of it.

Walt

 

Date: Wed, 6 Aug 1997 1:09:10 -0500

ICC/Midwest Adhoc Test Committee Open Action Items:

Dated 07/24/97 (Updated 08/05/97)

 

Items closed 07/24/97 will be moved to closed list after August 22 CC.

------------------------------------------------------------

ISSUE #:006a

DATE OPENED: 08/26/96

DESCRIPTION: Want to include the NPAC test plan as an appendix to this

test plan.

RESPONSIBILITY: Barry Bishop, Operations Team will contact Donna

Navickas, NPAC team

DATE DUE: 01/06/97

DATE CLOSED:

STATUS: Open

08/26/96 - New Item

08/30/96 - Walt Subora and Barry Bishop will be meeting with the NPAC

team on Sep. 10 and/or 11 to talk about testing, schedules, etc. Will

bring back to this team.

12/11/96 - Discussion of how NPAC would be incorporated.

Most NPAC test plans are currently proprietary. Since they can't be

incorporated in the public test plan, a characterization of the coverage

is necessary in the master test plan, to show that it has been covered.

Sect 4.2.4 of test plan will have a matrix or summary which

characterizes the coverage. Then, at the conclusion of testing,

Lockheed would have to provide documentation of the test results.

01/09/97 - Lockheed will provide the final Turnup Test plan for the

addendum after it is final.

02/13/97 - NPAC committee is formally constructing this test plan and we

will get an update at the next meeting.

04/08/97 - Plan is just about complete. Submit section under final

review. Will get a status after next NPAC meeting. Perhaps a draft

tomorrow.

06/12/97 - Walt will be going to next week s NPAC meeting. He hopes to

get a response then.

07/10/97 - The NPAC committee is still trying to get the testing done

and has not provided a write up for us. Walt Subora will send a letter

to Donna Navickas, NPAC chair, to ask for an expedited description for

inclusion in the test plan.

07/24/97 - Walt sent an e-mail to Donna Navickas, NPAC chair, asking for

an update to the test descriptions submitted in Dec, 1996 for inclusion

in the test plan (sect 4.2). If they feel it is OK as written, we will

close this issue, if they want to update, they will have until end of

August, 1997 or we will close and publish with what we have.

07/31/97 - Update - A new section was sent by Steve Markowski, Lockheed

Martin, for inclusion in the section. Bill Belshaw will include in issue

1.6.

------------------------------------------------------------

ISSUE #:024

DATE OPENED: 12/06/96

DESCRIPTION: Test team needs to determine failure scenario testing. IITP

tests will use a lab environment to run a broad range of failure

scenarios. How would this complement our efforts.

RESPONSIBILITY: : Team

DATE DUE: 02/11/97

DATE CLOSED:

STATUS: Open

12/06/96 - Walt will put on agenda for Dec. 11 meeting.

01/09/97 - Looping tests will be added to this section. Need to

investigate other scripts. Will see what NIIF (old IITP) can do that

will give confidence in June/July time frame.

03/11/97 - Joint meeting with SCP team on 04/08. Will try to cover

during this meeting.

04/08/97 - SCP team will submit to us some test scripts and Walt will

submit to NIIF/NT testing committee for inclusion.

05/15/97 - no change in status, although Walt gave an update on what the

NTC is looking at. He also highlighted some comparatively simple tests

in his lab and saw extensive looping. The currently implemented standard

is based on the XUDT message counts, which are not supported by anyone,

all use UDT messaging.

06/12/97 - Failure scenario testing - to be discussed during FCC

Guidance discussion.

07/10/97 - Joe Questore, Bellcore, coordinator for the NIIF NTC (nee

IITP) states that the are looking to do these kinds of tests in a

controlled test environment. They have developed test scripts for the

failure scenarios. Walt Subora will write a liaison letter to the NIIF

NTC to ask for the scripts or a write up on the test scripts for each of

the failure areas of interest to the FCC. The www.atis.org web site has

the documents, etc. for the Network Test Committee. See June meeting

minutes for what will be tested.

07/24/97 - Walt Subora still working on liaison letter to the NTC.

------------------------------------------------------------

ISSUE #:025

DATE OPENED: 12/06/96

DESCRIPTION: LEC-to-LEC interface tests are still not covered.

RESPONSIBILITY: All

DATE DUE: 02/13/97

DATE CLOSED:

STATUS: Open

12/06/95 - New item. Needs to have EDI interface firmed up

electronically. Also need tests for LEC to LEC interfaces when not EDI.

01/09/97 - To be provided by Operations team. Bill, MCI, will put

generic scripts in for the issue 1. Will be updated in next issue.

02/13/97 - Still open in Operations committee. These are pre-requisite

tests.

04/08/97 - Still open. Firmed up without Electronic interface on 4/10.

Operations team will work.

05/15/97 - Bill Belshaw is working on this. Update should come before

end of May.

06/12/97 - Bill Belshaw working on these. It is assumed these will be in

version 1.4.

07/10/97 - Repair scripts in section 4.3 and section 4.4 (operational

flows) are in issue 1.5 of test plan (soon to be available on

www.ported.com). The rest of section 4.3 is still being looked at to

come from the Operations committee.

07/24/97 - No update yet.

------------------------------------------------------------

ISSUE #:034

DATE OPENED: 01/08/97

DESCRIPTION: Put picture reference in for each test case. And if no

picture available, draw new one. Submit to Mr. Bill by close of business

on Jan. 15, 1997. Policy is to submit reference or draw new picture when

submit test cases.

RESPONSIBILITY: ALL

DATE DUE: 01/15/97

DATE CLOSED:

STATUS: Open

01/09/97 - New item.

02/13/97 - Still waiting for some of the drawings (Mack Dobkins - ISDN,

Andy Chalk - non-conforming end office, Nancy DeRoo - 911).

03/11/97 - Walt has been able to convert Nancy DeRoo s 911 drawings and

will send them to Bill.

04/08/97 - Nancy s drawings have been given to Bill, along with the test

scripts. They are also on ported.com under the 911 area.

05/15/97 - Walt suggested closing this issue and leave it to those

running ISDN tests to draw out for their own purposes. Will leave open

until the June meeting.

06/12/97 - The only area of concern is with ISDN. Because only Ameritech

(and perhaps Sprint) wants to test ISDN, it may not be a major concern.

Walt was planning to publish (via conference call) the tests that will

be run. This will close after the walk through of the ISDN scripts.

07/10/97 - ISDN test scripts to be discussed on 7/24 call.

07/24/97 - Only TCG and Ameritech will be running these tests. Walt will

make a proposal, with picture references for presentation to the

committee on August 22, 1997.

------------------------------------------------------------

Issue #:049

DATE OPENED: 07/24/97

DESCRIPTION: Turnover of test plan to Network Interconnection

Interoperability Forum/Network Installation Maintenance Committee

(NIIF/NIMC).

RESPONSIBILITY: Bill Belshaw, Walt Subora

DATE DUE: 10/15/97

DATE CLOSED:

STATUS: Open

07/24/97 New Issue. Will write a liaison letter to Alan Jones, NIIF/NIMC

coordinator, for turning over the test plan.

------------------------------------------------------------

Issue #:050

DATE OPENED: 07/24/97

DESCRIPTION: Cleaning up of/removal of GR references in the test scripts

before turnover to NIIF/NIMC.

RESPONSIBILITY: Bill Belshaw, Walt Subora

DATE DUE: 10/15/97

DATE CLOSED:

STATUS: Open

07/24/97 New Issue.

 

 

 

 

 

Content-Type: message/rfc822

 

Date: Wed, 6 Aug 1997 1:09:10 -0500

Message-Id: <"00120060807991/31229 IN-DECTSAP"@MHS>

 

July 24 ICC/Midwest Test Team conference call minutes

(Updated 08/05/97)

 

Thanks Barry Lewin, Bellcore for the minutes.

 

Attendees:

Carmen Colella, AIT

Robin Meier, AIT

Dick Dowd, LLC

Barry Lewin, Bellcore

Mitch Fuchs, AT&T

Rajeev Trika, TCG

Gene Johnston, GTE

 

Meeting began at 1:10 PM.

 

1. Robin Meier s issue - Turn over of test plan to (NIIF) Network

Interconnection Integration Committee NIMC Committee (Network

Installation and Management Committee) as of such-and-such a date and

Robin will present at the next meeting. Walt was hoping all changes

would be complete by mid-September and the plan could be submitted in

October. The cover letter to them needs to state the expectation that

the NIIF will be the keeper of it. Walt and Bill Belshaw will pull

together the draft of the letter. Address letter to Allan Jones. ACTION

ITEM FOR WALT AND BILL (AI-49).

 

2. Review of the SCP test scripts. Comments thus far: Bill Belshaw

wanted a better GR reference and Walt has updated and provided detail on

the reference. Walt will take the an ACTION ITEM (AI-50) back to Bill

Belshaw to work through the references. He will bring it back to the

committee as a whole at the next meeting. In the text scripts Walt

focused on overload testing and protocol errors. Walt asked that

everyone look over the scripts before the meeting. Bill will add these

to Issue 1.6 of the test plan. Relative to picture references, Walt is

working on them.

 

3. Issues around ISDN. Walt proposed (and group agreed) that the ISDN

test participants will work off-line to do a cut-down of the ISDN tests.

Walt will work with Rajeev off-line to do the selection and report back

to the Committee at the next meeting.

 

4. Review of Action Items:

Action Item 6 - closed based on what has been received from Steve

Markowski, Lockheed Martin

 

Issue 18 - closed last time.

 

Issue 24 - failure scenario testing - Walt is working on a liaison

letter with Joe Questore, Bellcore, to NIIF Network Testing Committee

(NTC) saying we want to reference their test plan.

 

Issue 25 - LEC-to-LEC interface test - Bill prepared scripts for this

(see Section 4.3)

 

Issue 26 - closed last time

 

Issue 28 - closed last time

 

Issue 30 - closed last time

 

Issue 32 - closed last time

 

Issue 34 - Walt suggested cutting ISDN down to make it a manageable set

for creating picture references.

 

Issue 47 - closed last time.

 

Issue 49 and Issue 50 opened this time

 

Final discussion - top priority should be to close out the test plan and

turn it over to the NIIF. There was concern expressed as to who should

be the keeper of these plans on a going-forward basis.

 

Walt will send out an e-mail proposing that the August 22 meeting be

turned into a conference call not to exceed 3 hours.